2021 Jan JK0-017 exam topics

Q31. A team member reports that a system component they are working on causes the system to continually reboot. The project manager should record this in which of the following documents? 

A. Quality management plan 

B. Communication plan 

C. Risk matrix 

D. Issue log 

Answer:


Q32. A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done? 

A. Move some of the task to another release. 

B. Have the team work over time and give them time off later to save the budget. 

C. Continue to work and complete the project as soon as possible. 

D. Review the plan with the team and develop a way to reduce the time 

Answer:


Q33. Which of the following is an input to a work breakdown structure (WBS)? 

A. Performance reports 

B. Stakeholder analysis 

C. Project scope statement 

D. Variance analysis 

Answer:


Q34. The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)? 

A. $35,624.00 

B. $59,373.33 

C. $71,248.00 

D. $85,497.60 

Answer:


Q35. Which of the following describes the LOWEST level of a work breakdown structure (WBS)? 

A. Technical specifications 

B. Project performance reports 

C. Work packages 

D. Functional specifications 

Answer:


Leading JK0-017 exam topics:

Q36. A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time. 

Which of the following will be impacted? 

A. Project scope will be impacted. 

B. Quality will be impacted. 

C. WBS will be impacted. 

D. SOW will be impacted. 

Answer:


Q37. A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing? 

A. Arrow Diagramming Method (ADM) 

B. Precedence Diagramming Method (PDM) 

C. Critical Path Method (CPM) 

D. Critical Chain Method (CCM) 

Answer:


Q38. A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur? 

A. Qualitative risk analysis 

B. Quantitative risk analysis 

C. Risk response planning 

D. Risk identification 

Answer:


Q39. Which of the following activities are associated with a project kick-off meeting? (Select Two). 

A. Obtaining a signature on the project charter. 

B. Communicating project goals and objectives. 

C. Communicating work package assignments. 

D. Creating a rough draft of the transition plan. 

E. Communicating stakeholder expectations. 

Answer: B,E 


Q40. Which of the following documents is used when soliciting vendors? 

A. Request for Proposal (RFP) 

B. Work Breakdown Structure (WBS) 

C. Statement of Work (SOW) 

D. Responsibility Assignment Matrix (RAM) 

Answer: