We have every one of the necessary CompTIA PK0-003 practice questions along with answers which are closely equal to the CompTIA PK0-003 actual exam. Your CompTIA CompTIA exam dumps are gathered and verified by way of multiple times. All the CompTIA PK0-003 exam syllabuses are included in our PK0-003 merchandise. The sort of CompTIA practice questions is the same because real CompTIA PK0-003 exam, thats multiple choice which can make you just as if on the genuine test day.

2021 Jan PK0-003 exam engine

Q51. - (Topic 2) 

A project has been identified as requiring input from many different areas. The project is anticipated to take two years to complete. Which of the following will be MOST useful in tracking progress toward completion? 

A. RACI matrix 

B. Risk log 

C. Transition plan 

D. Phase closure 

Answer:


Q52. - (Topic 1) 

A project team has to implement a key part of their solution from an external vendor. After sending out an RFP, the team has narrowed the possible providers down to three. Which of the following should the project manager do NEXT? 

A. Hold a steering committee meeting to discuss the options 

B. Ask the project team to take a vote on the vendor 

C. Begin contract negotiations with the lowest offer 

D. Contact project stakeholders individually and discuss the RFP 

Answer:


Q53. - (Topic 1) 

Please refer to the attached graphic and review the following task description. 

Which of the following is the project schedule critical path? 

A. A,E,F,B,G,H,D 

B. A,E,F,B,H,D 

C. A,G,H,D 

D. A,E,F,C,D 

Answer:


Q54. - (Topic 1) 

Which of the following is the purpose of a transition plan? 

A. It maps how the new business processes will flow after the project reaches completion 

B. It guides the project team on how to hand over the final product to the customer 

C. It delivers specialized training to new project team members 

D. It allows for smooth transition from one deliverable to the next 

Answer:


Q55. - (Topic 3) 

A project manager is drafting an internal communication plan with the assistance of the project team. Which of the following criteria are generally included in the internal communication plan? (Select THREE). 

A. Scope analysis 

B. Resource availability 

C. Stakeholder priorities 

D. Frequency of web-based meetings 

E. Quality reports 

F. Format of written communications 

G. Distribution lists 

Answer: D,F,G 


Refresh PK0-003 pdf exam:

Q56. - (Topic 3) 

Reviewing the results of a control chart, the project manager finds the production samples had results inside both the upper control limit and the lower control limit. Which of the following is the BEST course of action for the project manager based on this information? 

A. The project manager should identify potential new production teams to obtain different results. 

B. The project manager should create a report to outline the results for client review and request a more generous range between limits. 

C. The project manager should stop production until the processes are reviewed in full for identification of flaws. 

D. The project manager should continue following the existing process, including the measuring of samples for tracking. 

Answer:


Q57. - (Topic 2) 

A project manager is concerned that the project schedule will extend beyond initial estimation. Which of the following methods will allow the project manager to determine the project duration with the MOST precision? 

A. Gantt 

B. CCM 

C. CPM 

D. PERT 

Answer:


Q58. - (Topic 1) 

Senior executives within a company have noticed an increasing number of projects failing to deliver to requirements. Which of the following project governance methods will help to meet this need? 

A. Phase gate approval 

B. Project phase transition 

C. ISO standards compliance 

D. Audit trail 

Answer:


Q59. - (Topic 1) 

After identifying a change needed in the system, which of the following is the NEXT action the stakeholder should perform? 

A. Inform the developer 

B. Inform the resource manager 

C. Inform the project manager 

D. Inform the project sponsor 

Answer:


Q60. - (Topic 1) 

Which of the following can aid in the identification of the cause of the majority of the defects on a given project? 

A. Ishikawa diagrams 

B. Run charts 

C. Histograms 

D. Pareto charts 

Answer: