CompTIA CompTIA PK0-003 exam is certainly one of those nearly all favorable IT certifications which may promote the career opportunity for The idea professionals. If you successfully obtain your CompTIA PK0-003 certification, lots of career opportunities will open up for you personally. But firstly, you should set much hard work on the CompTIA PK0-003 exam preparation. It really is a demanding job if you get ready it by yourself. The actual candidates should have full command associated with all the features of the PK0-003 certification exam. The actual CompTIA PK0-003 online coaching course can benefit anyone a lot in preparing your CompTIA certification exam. The PK0-003 practice dumps contain each of the authorized knowledge items in accordance with all the PK0-003 exam syllabus.

2021 Dec PK0-003 actual test

Q11. - (Topic 1) 

An email to end users regarding the go-live of an upcoming software release is an example of: 

A. interactive method. 

B. push method. 

C. formal method. 

D. pull method. 

Answer:


Q12. - (Topic 2) 

The customer has significantly decreased the timeline on an active project. Which of the following is MOST likely to occur if the existing project scope is maintained? 

A. Quality will increase and cost will decrease 

B. Quality will decrease and cost will decrease 

C. Quality will decrease and cost will increase 

D. Quality will increase and cost will increase 

Answer:


Q13. - (Topic 2) 

Given the following activity: 

Provide details of errors within the software that occur during verification testing that provide enough evidence that allows the software developers to resolve the errors. 

Which of the following components is this known as within the quality management plan? 

A. Quality control 

B. Quality metrics 

C. Quality baseline 

D. Quality assurance 

Answer:


Q14. - (Topic 2) 

A project manager has uncovered that the optimal weight of the magnet that the stakeholders approved for the project is wrong. Which of the following BEST illustrates the problem? 

A. Pareto chart 

B. Ishikawa diagram 

C. PERT diagram 

D. Gantt chart 

Answer:


Q15. - (Topic 3) 

A task is estimated to take three days to complete but will not impact the critical path of the project for ten working days. Which of the following is the free float for the task? 

A. 3 days 

B. 7 days 

C. 10 days 

D. 13 days 

Answer:


Update PK0-003 free question:

Q16. - (Topic 2) 

A project manager wants to ensure that end users receive proper training prior to implementation. In which of the following documents should the project manager outline the necessary training? 

A. Work breakdown structure 

B. Transition plan 

C. Communication plan 

D. Lessons learned 

Answer:


Q17. - (Topic 3) 

Which of the following organizational structures is characterized by project team members who work in job-specific departments? 

A. Functional 

B. Projectized 

C. Strong matrix 

D. Matrix 

Answer:


Q18. - (Topic 3) 

A project manager has noticed that two of the resources will not talk to one another. The project manager brings the resources together to investigate the root cause of the communication issues. Which of the following conflict resolution techniques is the project manager using? 

A. Avoiding 

B. Smoothing 

C. Negotiating 

D. Confronting 

Answer:


Q19. - (Topic 3) 

Which of the following organizational structures is characterized by a group of dedicated project team members? 

A. Strong matrix 

B. Matrix 

C. Functional 

D. Projectized 

Answer:


Q20. - (Topic 3) 

If a representative of a business requests functionality to be included in the project that was not originally included in the project scope, the project manager should refer to which of the following plans? 

A. Issue Management Plan 

B. Quality Management Plan 

C. Risk Management Plan 

D. Change Management Plan 

Answer: