Q537. Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements? 

A. Perform Quality Control 

B. Quality Policy 

C. Perform Quality Assurance 

D. Quality Planning 

Answer:


Q538. In a weak matrix, the project managers role is: 

A. part-time 

B. full-time 

C. occasional 

D. unlimited 

Answer:


Q539. Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables? 

A. Estimate Activity Durations 

B. Sequence Activities 

C. Define Activities 

D. Activity Attributes 

Answer:


Q540. The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area? 

A. Project Communications Management 

B. Project Integration Management 

C. Project Risk Management 

D. Project Scope Management 

Answer:


Q541. Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document? 

A. Business case 

B. Work breakdown structure 

C. Requirements documentation 

D. Risk register 

Answer:


Q542. At the start of a typical project life cycle, costs are: 

A. low, peak as work is carried out, and drop as the project nears the end. 

B. low, become steady as work is carried out, and increase as the project nears the end. 

C. high, drop as work is carried out, and increase as the project nears the end. 

D. high, become low as work is carried out, and drop as the project nears the end. 

Answer:


Q543. Which quality tool may prove useful in understanding and estimating the cost of quality in a process? 

A. Checksheets 

B. Histograms 

C. Flowcharts 

D. Control charts 

Answer:


Q544. An intentional activity to modify a nonconforming product or product component is called: 

A. defect repair 

B. work repair 

C. corrective action 

D. preventive action 

Answer: