Opt for Pass4sure PMI-SP plus down load PMI-SP check inquiries to get a PMI-SP quiz official certifications. Pass4sure PMI-SP training thoughts are created along with thoughts, in addition to precise, plausible plus approved details. Each of our PMI-SP training quiz provides you with some sort of screening practical knowledge unmatched. Each of our PMI-SP training check thoughts plus PMI-SP are gaining knowledge from current plus energetic It pros who apply the example of making a person trained money for hard times.

2021 Jan PMI-SP test questions

Q41. Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

A. -$75,500

B. -$390,000

C. -$487,500

D. -$65,000

Answer: D


Q42. Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic.

What is hard logic?

A. Hard logic describes activities that can be completed in any order but are positioned with finish- to-start relationships.

B. Hard logic describes activities that have external constraints, such as a vendor.

C. Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.

D. Hard logic describes activities that must be completed in a particular order.

Answer: D


Q43. You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

A. -$48,654

B. 13 percent

C. -$225,000

D. 0.98

Answer: C


Q44. Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the work that is remaining in the project. Alice, one of Gary's project team members, consistently reports that she's late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is causing other delays in the project.

What is the review of the late work commonly called?

A. Variance analysis

B. Leadership

C. Quality control

D. Discipline

Answer: A


Q45. You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

A. Stakeholder classification

B. Project management team's classification

C. Assessment information

D. Identification information

Answer: B


Renew PMI-SP exam answers:

Q46. You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

A. Cost, with a variance of -$8,000

B. Schedule, with a variance of -$33,750

C. Cost, with a variance of $278,000

D. Schedule, with a variance of -$20,000

Answer: B


Q47. You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project.

How often should the report be created?

A. Weekly

B. One per status milestone reached

C. Regularly or on an exception basis

D. Exception-by-exception basis

Answer: C


Q48. CORRECT TEXT

Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

A. Application area

Answer: A


Q49. Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

A. Work performance measurement

B. Stakeholder expectation management

C. Project communication management

D. Stakeholder analysis

Answer: C


Q50. John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.

A. Concrete

B. Pre-construction

C. Engineering

D. Conceptual engineering

Answer: BCD