Want to know Examcollection PRINCE2-Foundation Exam practice test features? Want to lear more about PRINCE2-Exams PRINCE2 Foundation exam certification experience? Study Tested PRINCE2-Exams PRINCE2-Foundation answers to Leading PRINCE2-Foundation questions at Examcollection. Gat a success with an absolute guarantee to pass PRINCE2-Exams PRINCE2-Foundation (PRINCE2 Foundation exam) test on your first attempt.

2021 Oct PRINCE2-Foundation exam

Q81. - (Topic 2) 

What is the first task of product-based planning? 

A. Produce the Initiation Stage Plan 

B. Write the Project Product Description 

C. Identify dependencies 

D. Create the product breakdown structure 

Answer:


Q82. - (Topic 1) 

How many roles make up the Project Board? 

A. One 

B. Two 

C. Three 

D. Four 

Answer:


Q83. - (Topic 2) 

Which should be provided by corporate or programme management before the Starting up a Project process commences? 

A. A Project Brief 

B. Sufficient information to identify the prospective Executive 

C. The Project Initiation Documentation 

D. Authority to initiate a project 

Answer:


Replace PRINCE2-Foundation exam cost:

Q84. - (Topic 1) 

Which is a purpose of the Managing Product Delivery process? 

A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package 

B. Provide a controlled link between the Project Manager and the Team Manager(s) 

C. Enable the Project Board to request updates to the current Team Plan 

D. Establish solid foundations for the project 

Answer:


Q85. - (Topic 1) 

Which is a purpose of the Closing a Project process? 

A. Authorize the final stage of the project 

B. Confirm that all benefits defined in the Business Case have been achieved 

C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved 

D. Delegate day-to-day management of the end of the project to the Project Manager 

Answer:


Q86. - (Topic 2) 

Which of the following statements about customer's quality expectations and acceptance criteria are true? 

1. 

Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders. 

2. 

Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements. 

A. Only 1 is true 

B. Only 2 is true 

C. Both 1 and 2 are true 

D. Neither 1 or 2 are true 

Answer: