Q171. You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there maybe delays and wastebecause theproject team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario? 

A. This is an example of quality assurance. 

B. This is an example of a corrective action. 

C. This is an example of a preventive action. 

D. This is an example of team development. 

Answer: C 


Q172. Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits? 

A. Program architecture baseline 

B. Program risk register 

C. Program WBS D. Program charter 

Answer: D 


Q173. All of the following are benefits of a program except for which one? 

A. Resourcemanagement in aprogram allowsresources to be shared across all projects in the program. 

B. Projects can operate independently of one another. 

C. All projects follow the policies of the program and organization. 

D. The program manager can use the same approach in stakeholder management for all projects in the program. 

Answer: B 


Q174. You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign? 

A. Certificate of completion 

B. Proposal agreement 

C. Invoice 

D. Contract 

Answer: A 


Q175. You are the program manager for your organization and you need to define all of the program resources you'llneed for your program.All of the following can be considered a program resource except for which one? 

A. A forklift 

B. Materials for the installation of a new server 

C. A positive risk response 

D. Gary, an application developer 

Answer: C 


PgMP test questions

Most up-to-date PgMP test engine:

Q176. Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status? 

A. Change register 

B. Integrated change control 

C. Program Management Information System 

D. Change log 

Answer: A 


Q177. Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance? 

A. Value-added change requests 

B. Zero based budgeting 

C. Integrated change control 

D. Gold plating 

Answer: D 


Q178. What should a program manager do when a scope change has been approved that will drasticallyaffectthe program costsassuming that the costs willbeadded tothe program budget? 

A. Adjust the cost baseline 

B. Communicate cost of the change to all stakeholders 

C. Adjust the quality baseline 

D. Communicate the change to all stakeholders 

Answer: A 


Q179. Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme? 

A. Benefit management 

B. Stakeholder management 

C. Program governance 

D. Organizational planning 

Answer: D 


Q180. You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that mayaffect the overallcost of the program.Managementis concerned with how long it will take the program to reach the management horizon. What is management horizon also known as? 

A. Payback period 

B. Cost-to-benefits ratio 

C. Cost performance index 

D. Return on investment 

Answer: A