Your success in CompTIA PK0-004 is our sole target and we develop all our PK0-004 braindumps in a way that facilitates the attainment of this target. Not only is our PK0-004 study material the best you can find, it is also the most detailed and the most updated. PK0-004 Practice Exams for CompTIA Project+ PK0-004 are written to the highest standards of technical accuracy.

Q1. Which of the following documents does a vendor rely on to commit funding and resources to a project?

A. SOW

B. PO

C. SLA

D. MOU

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 299


Q2. A new project charter is being drafted.

Which of the following would be the BEST source for the high-level project requirements?

A. Sponsor

B. Project manager

C. Project management office

D. Project team

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 108


Q3. The client accepts the critical design review.

Which of the following meetings should be held to move to the NEXT step in the project?

A. Execution

B. Kickoff

C. Closure

D. Planning

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 112


Q4. Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

A. Sales clerk

B. Marketing representative

C. Team lead

D. Product item

Answer: B


Q5. The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

A. Balanced score card

B. WBS

C. Post-project evaluation

D. PERT

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 332


Q6. A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority.

Which of the following effects is this MOST likely to have on the project?

A. The deliverables and quality will remain the same, but the cost will increase.

B. The deliverables and quality will remain the same, but the cost will decrease.

C. The deliverables and cost will remain the same, but the quality will increase.

D. The cost and quality will remain the same, but the deliverables will increase.

Answer: A


Q7. Which of the following describes how a project is related to a program?

A. A program is a combination of multiple projects.

B. A program contains an element of the project.

C. A program is a part of a project.

D. A program uses half of the project’s budget.

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.72


Q8. A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.

Which of the following is the FIRST step the project manager should take?

A. Assess the risk register’s new items.

B. Review the task start and finish dates.

C. Obtain additional resources.

D. Analyze the assigned hours.

Answer: A