Ucertify offers free demo for PMI-SP exam. "PMI Scheduling Professional Practice Test", also known as PMI-SP exam, is a PMI Certification. This set of posts, Passing the PMI PMI-SP exam, will help you answer those questions. The PMI-SP Questions & Answers covers all the knowledge points of the real exam. 100% real PMI PMI-SP exams and revised by experts!

Q89. The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

A. Activity list

B. Milestone list

C. Activity attributes

D. Project document updates

Answer: D


Q90. You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

A. $2,975,000

B. 1.02

C. $139,306

D. $2,380,000

Answer: D


Q91. You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

A. Work performance measurements

B. Corrective actions

C. Trim the project scope

D. Causes of variances

Answer: B


Q92. You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

A. Project is behind the schedule.

B. Costs are higher than planned.

C. Project is right on target.

D. Project is ahead of the schedule.

Answer: D


Q93. Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

A. Communications management plan

B. Stakeholder register

C. Requirements

D. Stakeholder management strategy

Answer: B


Q94. You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?

A. Actual durations need to be recorded to track process improvement.

B. Actual durations need to be recorded to create the schedule baseline.

C. Actual durations need to be recorded to measure the actual progress of the project.

D. Actual durations need to be recorded to perform quality control on the project management processes.

Answer: C


Q95. You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule.

Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

A. Project calendar

B. Resource calendar

C. Organizational calendar

D. Company calendar

Answer: A


Q96. You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

A. 284,635

B. 570,025

C. 569,270

D. 755

Answer: A