Master the PRINCE2-Foundation PRINCE2 Foundation exam content and be ready for exam day success quickly with this Exambible PRINCE2-Foundation test engine. We guarantee it!We make it a reality and give you real PRINCE2-Foundation questions in our PRINCE2-Exams PRINCE2-Foundation braindumps.Latest 100% VALID PRINCE2-Exams PRINCE2-Foundation Exam Questions Dumps at below page. You can use our PRINCE2-Exams PRINCE2-Foundation braindumps and pass your exam.
PRINCE2-Exams PRINCE2-Foundation Free Dumps Questions Online, Read and Test Now.
NEW QUESTION 1
Which management product is used to record relationships between specialist products?
- A. Change control approach
- B. Configuration item record
- C. Issue register
- D. Product status account
Answer: B
NEW QUESTION 2
What is a goal of the 'implement' step within the recommended risk management procedure?
- A. To prepare specific management responses to identified risks
- B. To monitor the effectiveness of actioned risk responses
- C. To estimate the risk to the project in terms of probability and impact
- D. To communicate information related to the risks faced by the project
Answer: C
NEW QUESTION 3
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
- A. Benefits
- B. Quality
- C. Risk
- D. Scope
Answer: B
NEW QUESTION 4
Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.
- A. benefits
- B. dis-benefits
- C. issues
- D. risks
Answer: A
Explanation:
A Benefit is the measurable improvement resulting from an outcome that is perceived as an advantage by one or more stakeholders.
Reference
http://p2.tech-academy.co.uk
NEW QUESTION 5
Which characteristic distinguishes a project from regular business operations?
- A. Produces benefits
- B. Introduces business change
- C. Manages stakeholders
- D. Incurs cost
Answer: B
NEW QUESTION 6
Which is a purpose of the 'controlling a stage' process?
- A. To produce a team plan for the work to be assigned to a team manager
- B. To select and implement actions that will resolve deviations from a plan within tolerance
- C. To obtain approvals for products delivered in a work package
- D. To update a project plan to incorporate the actuals from a stage plan
Answer: B
Explanation:
Reference
http://prince2.wiki/Controlling_a_Stage#Purpose
NEW QUESTION 7
Which is a FALSE statement about technical stages?
- A. Can overlap with other technical stages
- B. Typified by the use a particular set of specialist skills
- C. Include the Managing a Stage Boundary process activities
- D. Can span more than one management stage
Answer: C
NEW QUESTION 8
How many tasks does the product-based planning technique describe?
- A. One
- B. Two
- C. Three
- D. Four
Answer: D
NEW QUESTION 9
Which process provides information for the project board to review an updated project plan?
- A. Initiating a project
- B. Controlling a stage
- C. Directing a project
- D. Managing a stage boundary
Answer: C
NEW QUESTION 10
Which is a purpose of the Managing a Stage Boundary process?
- A. Provide the Project Board with sufficient information for approving the next stage
- B. Approve the next Stage Plan
- C. Review and close any risks and issues identified during the previous stage
- D. Control the link between the Project Manager and the Team Manager(s)
Answer: A
NEW QUESTION 11
Which is an objective of the Managing Product Delivery process?
- A. Sign-off completed Work Packages
- B. Ensure the Business Case is kept under review
- C. Report progress to the Project Board
- D. Ensure that work on products is authorized and agreed with the team
Answer: D
NEW QUESTION 12
Which is a minimum requirement for applying the risk theme?
- A. Threats must be assessed for their impact on the viability of the project
- B. A single role that is responsible for all risks must be defined
- C. The PRINCE2 risk management procedure must be followed
- D. Team managers must maintain their own risk registers
Answer: A
Explanation:
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/
NEW QUESTION 13
What should be implemented using a risk budget?
* 1. A request for change
* 2. A contingent plan
* 3. Actions to avoid a risk from occurring
* 4. Responses to dis-benefits
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
Answer: A
NEW QUESTION 14
The application of which principle helps to define what should be included in a project?
- A. Defined roles and responsibilities
- B. Focus on products
- C. Manage by stages
- D. Continued business justification
Answer: C
NEW QUESTION 15
Why is a Project Brief produced?
- A. To act as a trigger for the Starting up a Project process
- B. To record the strategies and management controls to be used by a project
- C. To provide a full and firm foundation for the initiation of a project
- D. To be used by the Project Board as a basis for reviewing the progress of a project
Answer: C
NEW QUESTION 16
......
Thanks for reading the newest PRINCE2-Foundation exam dumps! We recommend you to try the PREMIUM Certleader PRINCE2-Foundation dumps in VCE and PDF here: https://www.certleader.com/PRINCE2-Foundation-dumps.html (463 Q&As Dumps)