Examcollection PMI-001 Questions are updated and all PMI-001 answers are verified by experts. Once you have completely prepared with our PMI-001 exam prep kits you will be ready for the real PMI-001 exam without a problem. We have Far out PMI PMI-001 dumps study guide. PASSED PMI-001 First attempt! Here What I Did.

Q465. The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as: 

A. recognition and rewards 

B. compliance 

C. staff acquisition 

D. training needs 

Answer:


Q466. Within project integration management, the statement of work (SOW) references which aspects of the project? 

A. Strategic plan, business need, and product scope description 

B. Contract, enterprise environmental factors, and organizational process assets 

C. Business plan, project management plan, and project schedule 

D. Product lifecycle, business objective, and management strategy 

Answer:


Q467. Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance? 

A. Schedule network analysis 

B. Reserve analysis 

C. Alternative analysis 

D. Variance analysis 

Answer:


Q468. When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized? 

A. Interactive communication 

B. Claims administration 

C. Conflict management 

D. Performance reporting 

Answer:


Q469. Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique? 

A. Expert judgment 

B. Forecasting methods 

C. Earned value management 

D. Analytical techniques 

Answer:


Q470. What type of reward can hurt team cohesiveness? 

A. Sole-sum 

B. Win-lose 

C. Lose-win 

D. Partial-sum 

Answer:


Q471. Which of the following is a tool or technique of the Define Activities process? 

A. Rolling wave planning 

B. Precedence diagramming method (PDM) 

C. Alternatives analysis 

D. Parametric estimating 

Answer:


Q472. Projects are undertaken by an organization to support the: 

A. Product performance. 

B. Budget process. 

C. Collective capabilities. 

D. Organizational strategy. 

Answer: