PMP PMP exam is one of the the majority of demanded exams to check whether anyone master the crucial topics of the PMP exam. Its never a good easy work to pass the particular PMP PMP certification exam by yourself. However, Testkings PMP PMP practice questions and also answers will help you to pass on the first try out. PMP PMP simulated tests are gathered under the particular supervision of skilled and skilled IT specialists. PMP PMP exam preps which provide you with the most realistic and also comprehensive studying materials are generally award-winning of the exact same occupation. Get access to the free PMP PMP exam braindumps on Testking website proper now.

2021 Aug PMP practice test

Q181. Which of the following must not performed in the project initiation process?

A. Evaluate historical information

B. List down business need

C. List down stakeholders

D. Create scope statement

Answer: D


Q182. What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

A. $115

B. $138

C. $140

D. $165

Answer: C


Q183. Which technique is utilized in the Schedule Control process?

A. Performance Measure

B. Baseline Schedule

C. Schedule Comparison

D. Variance Analysis

Answer: D


Q184. Which tool and technique uses a statistical relationship between historical data and other variables to calculate estimates?

A. Analogous estimating

B. Three-point estimates

C. Parametric estimating

D. Bottom-up estimating

Answer: C


Q185. Which tool or technique measures performance of the project as it moves from project initiation through project closure?

A. Resource leveling

B. Parametric measuring

C. Pareto chart

D. Earned value

Answer: D


PMP practice exam

Replace PMP free practice exam:

Q186. You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent?

A. Balanced matrix organization

B. Functional organization

C. Projectized organization

D. Weak matrix organization

Answer: C


Q187. A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?

A. Resource leveling

B. Schedule compression

C. Critical chain

D. Adjusting leads and lags

Answer: B


Q188. You are about to begin negotiations with people from another country. Which of the following should provide guidance on what business practices are allowed and not allowed?

A. The company code of conduct

B. The project charter

C. The scope management plan

D. The negotiation plan

Answer: A


Q189. The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?

A. Crashing

B. Floating

C. Leveling

D. Fast tracking

Answer: C


Q190. For communication to occur, there must be:

A. All of the other alternatives apply

B. a communication process

C. Two or more people involved

D. the transmittal of information

E. The transmittal of information and a communication process

Answer: A