we provide Pinpoint PRINCE2-Exams PRINCE2-Foundation latest exam which are the best for clearing PRINCE2-Foundation test, and to get certified by PRINCE2-Exams PRINCE2 Foundation exam. The PRINCE2-Foundation Questions & Answers covers all the knowledge points of the real PRINCE2-Foundation exam. Crack your PRINCE2-Exams PRINCE2-Foundation Exam with latest dumps, guaranteed!

Online PRINCE2-Foundation free questions and answers of New Version:

NEW QUESTION 1

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

  • A. Defined acceptance criteria
  • B. the PRINCE2 principles
  • C. the terminology used
  • D. the number of themes applied

Answer: D

NEW QUESTION 2

Which is an objective of the Closing a Project process?

  • A. Prepare the plan for the next stage
  • B. Assess any benefits that have already been realized
  • C. Produce a Benefits Review Plan to identify what benefits are expected
  • D. Check that all benefits are realized before closing a project

Answer: B

NEW QUESTION 3

Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Select and implement actions that will resolve deviations from a plan within tolerance
  • C. Obtain approvals for products delivered in a Work Package
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: B

NEW QUESTION 4

Which statement about the length of management stages in a project is CORRECT?

  • A. A higher level of major risk will require a stage to be longer
  • B. Stage length is influenced by project board availability
  • C. A higher level of major risk will require a stage to be shorter
  • D. Use of management stages represents a time driven control

Answer: C

NEW QUESTION 5

Which is NOT one of the PRINCE2 integrated elements?

  • A. Tailoring PRINCE2 to the project environment
  • B. The processes
  • C. The products
  • D. The themes

Answer: C

NEW QUESTION 6

Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Plan
  • C. Communication Management Strategy
  • D. Project Product Description

Answer: A

NEW QUESTION 7

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

  • A. A description of the risk management procedure
  • B. An explanation of the company's risk appetite
  • C. The names of the assigned actionees for each risk
  • D. Estimations of the likelihood and impact of risks

Answer: A

Explanation:
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/

NEW QUESTION 8

Who are considered as the stakeholders in a project?

  • A. Only those benefitting the project
  • B. Everyone in the corporate organization
  • C. Everyone involved in or affected by the project
  • D. Only those who are users of the products

Answer: C

NEW QUESTION 9

Which theme verifies that a project's products are fit for purpose?

  • A. Business case
  • B. Organization
  • C. Quality
  • D. Progress

Answer: C

Explanation:

Reference
http://prince2.wiki/Quality

NEW QUESTION 10

Which process is used to define how baselines will be established and controlled?

  • A. Controlling a stage
  • B. Directing a project
  • C. Initiating a project
  • D. Starting up a project

Answer: D

Explanation:

Reference
http://prince2.wiki/Quality

NEW QUESTION 11

How is the tailoring approach defined for a project?

  • A. The project board approves the approach
  • B. The project board documents the approach
  • C. Project assurance approves the approach
  • D. Project assurance documents the approach

Answer: A

NEW QUESTION 12

What must a PRINCE2 project demonstrate?

  • A. Application of PRINCE2 principles
  • B. Application of proper leadership skills
  • C. Application of the activities in each process
  • D. Application of tools appropriate for the industry

Answer: A

NEW QUESTION 13

Which is a purpose of the 'initiating a project' process?

  • A. To decide if it is worthwhile to initiate a project
  • B. To decide on the project approach
  • C. To establish solid foundations for a project
  • D. To identify the number of work packages required

Answer: C

Explanation:
Reference
http://prince2.wiki/Initiating_a_Project#Objective

NEW QUESTION 14

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

  • A. Directing a project
  • B. Managing product delivery
  • C. Managing a stage boundary
  • D. Initiating a project

Answer: B

Explanation:
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

NEW QUESTION 15

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by stages
  • B. Manage by exception
  • C. Continued business justification
  • D. Learn from experience

Answer: A

Explanation:
Reference https://www.whatisprince2.net/prince2-theme-plans.php

NEW QUESTION 16
......

100% Valid and Newest Version PRINCE2-Foundation Questions & Answers shared by Certleader, Get Full Dumps HERE: https://www.certleader.com/PRINCE2-Foundation-dumps.html (New 463 Q&As)